|

ALCAN
G3 Expansion Project

Project Status |
Completed - December 2007 |
Project Description |
12 Flocculent facility process tanks
Structural Steel Work
Pipe-work Packages
Fabricate and stainless line Lime silo |
Location |
Fabricate pre assembled modules shipped to Gove for installation by our Client |
Alcan

Initial Project Completion |
Ongoing |
Project Description |
Fabricate and develop two Needle tanks
Fabricate and develop two TCA Reactor tanks
Fabricate and develop three Surge tanks |
Location |
Fabricate and ship to Gove for installation by our Client |
Fluor Daniel
Mc Arthur River Mine

Project Status |
Completed - June 1996 |
Project Description |
Fabricate, deliver, install and commission of
Structural Steel, Mechanical and Piping
Installations in stock pile R.O.M and grinding areas
Mechanical installation of Ball Mill & Conveyors
Plate work / tanks, including stainless steel tanks
Concentrator Deferred Flotation structural mechanical and piping installation
|
Location |
Fabricate in Darwin, delivered & assembled on site |
GL&V / McArthur River Mine
36m Tailings Thickener Tank / Structural Works

Project Status |
Completed - July 2008 |
Project Description |
Fabricate and process material in packages and transport to site
Assemble, erect & commission on site
Sandblast & protective coat structures prior to departure
Sandblast & protective coat all remaining structure on site
|
Location |
Fabricate in Darwin, and completed on site |
Compass Resources
Browns Oxide Mine Thickener Tanks / Acid Tank

Project Status |
Completed - 2007 |
Project Description |
Fabricate and process material in packages and transport to site
Assemble, fabricate and erect on site
Sandblast & protective coat structures prior to departure
Sandblast & protective coat all remaining structures on site
|
Location |
Fabricate in Darwin, and completed on site |
Baker Hughes
East Arm Port / Dampier - Woodside Supply Base

Project Status |
Completed - June 2002 |
Project Description |
Design & fabricate / Blast & paint storage silos
Pressure vessels
Cutting bottles & associated steelwork
Pipelines
Site preparation including earth works & concrete
Site installation & commissioning
|
Location |
Fabricate in house, transported by sea, assembled & commissioned on site |
Bechtel
Darwin LNG Plant

Project Status |
Completed - July 2005 |
Project Description |
Supply / Fabricate strucural platforms
Apply approved coatings to pipe spools
Design & fabricate four tanks
Pre-fabricate LNG Tank roof sections
Design & Fabricate covered walkways
|
Location |
Fabricated in house, and transported to site in modules |
Signet Engineering
Brocks Creek Gold Mine

Project Status |
Complete - May 1996 |
Project Description |
Mine plant construction, installation & commissioning
All structural & mechanical installations
All plate work for various tanks
Blasting and painting of tanks in situ
|
Location |
Fabricated, install & commission on site |
|
|
|